Shweli-3 Hydropower Project


The placement of reinforced concrete for Diversion Culvert of Shweli-3 Hydro power Project

The placement of reinforced concrete for Diversion Culvert of Shweli-3 Hydro power Project at a distance of 12 miles in the north of Mong Mit, Northern Shan State has been implemented by the Department of Hydro Power Implementation under the Ministry of Electricity and Energy of the Union of Government of Myanmar, using the fund of overhead expenditure for the financial year 2015-2016.

The Company had won the tender bidding for this Diversion Culvert project both in 2015-2016 fiscal year and 2016-2017 fiscal year. The projects earned the Company for a reasonable profit.

 

The salient points of the project
Project NameShweli-3 Hydro Power Project
Project LocationMong Mit, Northern Shan State
Installed Capacity1,050 MW
Type of WorkPlacement of Reinforced Concrete for Diversion Culvert
ClientDepartment of Hydro Power Implementation, the Ministry of Electricity and Energy.
Construction Period for First Contract5-month
Date of CommencementAugust 21, 2015
Construction Period for Second Contract2-month
Date of CommencementJanuary 5, 2017